Due to human error, the connection between the new datacenter switches and the central router was interrupted.
- Type
- interruption
- Begin
- 2021-12-15 12:45:00
- End
- 2021-12-15 13:42:00
- Duration
- 57m0s
- Affected
- all 25 gigabit connected machines (shares, websites, clusternodes)
- Source
- cpk/1290.md
- Created
- 2021-12-15 12:45:00
- Updated
- 2026-05-05 08:55:08